Several bridge projects are approaching in Putnam County.
Bridge #191, located on 1000 S, east of 625 E, is scheduled to close on or around September 1, to facilitate a full replacement. The closure is expected to last approximately one month, pending favorable weather conditions and construction progress.
Bridge #124 located on 150W south of Buzzi Cement plant, is scheduled to close on or around September 8, to facilitate a full replacement. The closure is expected to last approximately 60 days, pending favorable weather conditions and construction progress.
After the completion of bridge #124 the contractor will move forward to bridge #122 then #123. (which is included in the 60 days) .