Lighting for Randolph Street bridge project nearly complete

Monday, October 13, 2025 at 2:00 AM

By Kathy Bottorff

The October 10report from USI Consultants on the Randolph Street Bridge replacement project shows the project at 86% complete.

The report states that Michiana Contracting of Plymouth worked on light pole foundations last week. They also work on the wiring and setting light poles and luminaires. 

This week, Michiana Contracting should finish all lighting and have the lights energized. E & B Paving is scheduled for early in the week to complete paving, and Slusser plans to come in later this week and place seed and sod. 

The county’s $3 million bridge project is estimated to be completed by October 31.