This past week, LaPorte Construction completed all the sidewalk and bridge railing work for the Randolph Street Bridge Replacement Project. They also smoothed all the concrete for the rail and piers and completed all concrete work.
ABC Grooving was in and has grooved the bridge deck. Michiana Contracting has placed the lighting handholes and most of the cable duct.
Last week, the park department reset its bricks in the new walk.
Toward the end of this week, Michiana Contracting may be on site to continue with the lighting work. They still need to finish the cable duct, foundations, service point, and set the poles and lights.
E&B Paving is expected to pave the surface around October 7th. Once the lighting project is complete, Slussers Green Thumb will be in to complete the seeding, and once the pavement is done, then striping can be done.
LaPorte Construction will not be on site this week because any remaining work cannot be completed until the subcontract work is finished.
LaPorte Construction estimates they are 86% complete with the project.
Indiana Weekly Gas Price Update shows prices falling
Parke, Putnam and Vermillion counties now eligible for FEMA assistance
Several fundraisers are planned to benefit the Montezuma family and fight back against Alzheimer's
Postal Service recommends 2026 holiday mailing and shipping dates
Attorney General Todd Rokita calls on Hoosiers to claim compensation for inflated generic drug prices
Pennsylvania Attorney General's Cold Case Section, Erie investigators announce arrest of Brazil, IN man in 2002 rape, murder
Impaired driver taken to hospital then jail after crash
Gov. Braun announces plan for new, larger campground at McCormick’s Creek State Park
Governor Braun proclaims Indiana Rail Safety Week September 21-27
State unemployment rate remains below national average
Indiana weekly gas price update
Riverton Parke looks to continue momentum
Parke County Community Foundation awards funds for Ritz renovations
USDA announces 2026 and 2027 enrollment for key price and revenue safety net programs, first base acre increase in two decades