The $3 million bridge replacement project on Randolph Street in Plymouth is 52% complete, according to contractors LaPorte Construction.
Last week, LaPorte Construction drove piling for bent 4. All the piles have been driven to bearing and cut and filled with concrete. Forms were placed, and Fort Wayne Reinforcement installed the rebar in bent #4, and the bent was poured on Friday. LaPorte also placed some rip-rap on the north bank, and the overhangs, decking, and deck pans on beam spans one and two.
This week, LaPorte Construction plans to finish placing all the riprap on the north and south banks as well as pouring the upper portion of bent 1. The last set of beams is scheduled for delivery and placement on July 21st. They also plan to install the end bent drains on both sides of the bridge.
New milestones and completion dates have been discussed with INDOT and the contractor. Marshall County and the City of Plymouth have both agreed on the dates, and the agreement has been sent to the contractor for review and signatures so it can be passed on to the county.
According to USI Consultants and LaPorte Construction, the project is on schedule. While the entire project isn’t expected to be complete by the Blueberry Festival, the bridge should be open to pedestrian and tram traffic.

Photos provided.
Lawrenceville receives federal E.P.A. report on public water system
Knox County tornado assessment issued by the NWS
Knox County farm to be featured Friday at Indiana State Fair
St Francisville looking to curb speeding on recently repaired bridge
IDPH announces it is not adopting new vaccination guidelines
Bridgeport undergoes OHSA inspection and cleaning of water wells
Sumner formally applies for state grant
Yochum Indiana State Senate campaign derailed
Three arrested in domestic incidents in Lawrenceville
Indiana Department Of Health, IU School of Medicine to improve rural ER obstetric, pediatric care
Illinois Transportation Enhancement Program application period is open
Salyers stepping down from Lawrence County Chamber
17 miles of U.S. 40 paving in Clark County
Traffic patterns to change for Illinois State Fair
National 811 Day reminds you to call before you dig